Project scheduling techniques are the methods a project manager uses to turn a list of tasks, durations and dependencies into dates that can be defended. The core set is the critical path method (CPM), PERT three point estimating, Gantt charts, critical chain, resource leveling and resource smoothing, the two compression techniques (fast tracking and crashing), rolling wave planning and Monte Carlo simulation. Each one answers a different question, and picking the wrong one is how a schedule that looked fine in week one becomes a missed deadline in week six.
This guide runs all of them on the same small project, a five task website relaunch for a client, so you can see what each technique actually changes. The critical path says the job takes 21 days. Three point estimates move the expected finish to 23 days, and a 10,000 run simulation puts the chance of hitting day 21 at roughly 7%. Most of what follows is about closing that gap, or at least admitting it to the client before the project starts.
- What project scheduling is
- Which project scheduling technique to use when
- Critical path method
- PERT and three point estimates
- Gantt charts
- Critical chain
- Resource leveling vs resource smoothing
- Fast tracking vs crashing
- Rolling wave planning
- Monte Carlo simulation
- Where schedules break
- After the schedule is set: estimated vs actual hours
- FAQ
What project scheduling is
Project scheduling in project management is the step that assigns dates to work that has already been scoped and estimated. The Association for Project Management defines a schedule as a timetable of forecast start and finish dates for activities, and it describes two main approaches to building one: critical path and critical chain. Everything else in this guide either feeds those two (better duration estimates), adjusts them (leveling, smoothing, compression) or tests them (simulation).
Three inputs have to exist before any technique works. You need the work broken into tasks, usually through a work breakdown structure, a duration for each task, and the dependencies between tasks. If you are still producing the duration numbers, the methods for that are covered in our guide to project estimation techniques. This article starts where estimation ends.
The running example has five tasks:
| Task | Duration (most likely) | Depends on |
|---|---|---|
| A. Requirements and sign off | 4 days | Nothing, it starts the project |
| B. Design | 6 days | A |
| C. Content | 3 days | A |
| D. Build | 8 days | B |
| E. Test and launch | 3 days | C and D |
All figures in the examples are illustrative, and money is in US dollars.
Which project scheduling technique to use when
The quickest way to choose among scheduling methods in project management is to name the problem first. A technique that answers “how long will this take” does nothing for “the same designer is booked twice on Tuesday”.
| Technique | Use it when | What it costs you |
|---|---|---|
| Critical path method | Durations are fairly well known and you need the minimum project length and the tasks that drive it | Assumes unlimited people, so the date it gives can be unreachable |
| PERT | Durations are uncertain and someone asks how likely a date is | Three estimates per task; ignores the risk that a second path becomes critical |
| Gantt chart | You need to show the schedule to a client or a team | Displays dates but calculates nothing by itself |
| Critical chain | Key people are shared and every task estimate carries hidden padding | Requires the team to accept aggressive task estimates and a visible buffer |
| Resource leveling | Someone is overbooked and the end date may move | Usually a later finish |
| Resource smoothing | Someone is overbooked and the end date may not move | Only works inside the available float |
| Fast tracking | The deadline moved earlier and tasks can partly overlap | Rework risk |
| Crashing | The deadline moved earlier and money is easier to find than time | Extra labor cost, overtime fatigue, onboarding time |
| Rolling wave planning | Later phases cannot be detailed yet | The finish date stays a range until later waves are detailed |
| Monte Carlo simulation | The date is a commitment with penalties or a fixed launch | Needs software and honest ranges for every task |
Critical path method
The critical path is the longest chain of dependent tasks from start to finish, and its length is the shortest time in which the project can be done. A Carnegie Mellon construction management text calls CPM the most widely used scheduling technique, and software handles networks with thousands of activities. Any delay to a task on the critical path delays the finish by the same amount.
For the relaunch, the calculation is a forward pass over each path:
Those 11 days of float on content are the useful part of the result. They tell you the writer can start late, take another job first or slip a week without touching the launch date. Float has its own formulas and types, which we cover in detail in slack time in project management. If you want a ready grid for the forward and backward pass, there is also a free critical path method template.
The weakness of CPM is that it looks only at task dependencies. An article in PMI’s PM Network points out that it assumes resources are available in unlimited quantities, so a 21 day answer can hide the fact that one person is booked on two critical tasks at once. That is the problem leveling and critical chain were built to fix.
PERT and three point estimates
PERT (program evaluation and review technique) replaces each single duration with three: optimistic (O), most likely (M) and pessimistic (P). The expected duration is (O + 4M + P) / 6, and the spread of each task is roughly (P − O) / 6. PMI’s Practice Standard for Scheduling describes the weighting as a manual approximation of a statistical distribution.
Why bother? A paper presented at a PMI Global Congress argues that a schedule built on single duration figures gives you roughly a 50/50 chance of finishing on time, while three point estimates raised that to about 73% in the author’s experience. Most PERT examples stop at one task. The useful step is to add up the critical path:
The 21 day critical path is the most likely figure for every task added together, and it has less than a one in five chance of holding. The pessimistic tails are longer than the optimistic ones, which pushes the expected finish two days later. As a sensitivity check, if the team cuts the worst case for Build from 16 to 12 days (by freezing scope before it starts, say), the expected finish drops to 22.3 days and the chance of day 21 rises to about 23%. The biggest spread on the path is where reducing uncertainty pays off most.
In construction, where task durations are well understood, practitioners tend to use plain CPM and rarely run PERT. PERT earns its keep on research, design and software work where nobody has built this exact thing before.
Gantt charts
A Gantt chart is a presentation format. It draws each task as a bar on a calendar and the links between bars as arrows, so a client can see in ten seconds that testing starts on day 18. APM notes that the output of most scheduling techniques is usually presented as bars on a timeline. The chart is only as correct as the CPM logic behind it, and a Gantt chart with hand dragged bars and no dependencies will not recalculate when Design slips by two days.
For chart elements, examples and how to build one step by step, see our full guide to the Gantt chart. If you need a filled in example of a whole schedule to adapt, use the free project schedule template, or download it below.
Critical chain
Critical chain starts from the critical path and then accounts for people. APM describes it as a resource based approach that protects chains of activities with buffers and tries to keep resources at a constant level of use. It targets two habits that quietly waste float: switching between tasks, and starting work at the last possible moment because the estimate allows it. PMI’s practice standard defines the critical chain as the longest resource leveled path through the schedule, buffers included.
The mechanics are simple even if the culture change is hard. Each task estimate is cut to an aggressive figure without personal padding, and the removed safety is pooled into one project buffer at the end. On the relaunch, the critical tasks drop from 4, 6, 8 and 3 days to 3, 4, 6 and 2 days, which removes 6 days. This example keeps half of that as a project buffer, so the committed length is 15 + 3 = 18 days. The manager then watches buffer consumption instead of individual task dates. If Build overruns by 2 days, two thirds of the buffer is gone, and that is the signal to act, long before the end date is visibly at risk.
The method fails when management treats the aggressive estimates as promises and blames people for missing them. The whole point is that half the tasks will run over and the buffer absorbs it.
Resource leveling vs resource smoothing
Both techniques fix overbooked people. The difference is whether the end date is allowed to move.
- Resource leveling resolves overallocation even if the project finishes later. A PMI paper on leveling notes that the project completion is pushed out further the more resources you level.
- Resource smoothing treats the finish date as fixed. In a time constrained approach, critical path activities cannot be altered and other activities shift only within their slack.
On the relaunch, suppose one designer does both Design (B) and Content (C), and both are scheduled to start on day 4. That person is booked for two days of work every day from day 4 to day 7.
The second case is common on real teams and invisible to plain CPM. Leveling also moves the critical path itself: after it runs, Content is critical and Build is not. The same surprise hits larger projects harder. Two people assigned 650 days of effort cannot finish in fewer than 325 working days, and when the software levels such a schedule, the finish moves out by months. The delay was always there; leveling only made it visible on the chart.
Fast tracking vs crashing
Both are schedule compression techniques for when the deadline moves earlier. PMI describes the choice as either crashing, which shortens activities by adding resources, or fast tracking, which runs normally sequential tasks in parallel. Only tasks on the critical path are worth compressing, because shortening anything else saves no time at all.
The client now wants the relaunch in 18 days instead of 21. Crashing works from the cost slope, the extra cost per day saved, and buys the cheapest days first:
Fast tracking gets the same result differently. Testing starts 2 days before Build finishes, on the parts of the site that are already done. That costs no extra hours unless something has to be redone. Say there is a 40% chance of 12 hours of rework at $100, which is an expected cost of $480.
| Option to save 3 days | Extra cost | Main risk |
|---|---|---|
| Crash Design 1 day and Build 2 days | $1,960, certain | A new developer slows the others while learning the codebase |
| Crash Design 1 day and fast track Test 2 days | $360 certain plus $480 expected rework, $840 in total | If rework happens it also costs time, and part of the gain is lost |
| Move the deadline | $0 in labor | The client relationship, if the date was a promise |
Fast tracking looks cheaper on paper, and a PMI feature on the technique warns that it almost always results in increased risk and may bring rework that cancels part of the gain. The sensible order is to overlap only tasks whose inputs are stable, crash only where a qualified person can start immediately, and recompute the critical path after every cut, because a second path can become critical once the first one shrinks. Adding people late is the classic crashing trap. New people help a late project mainly when they already know the domain and the work splits into pieces they can own without constant handoffs.
Rolling wave planning
Rolling wave planning details the near term work fully and keeps later work as rough planning packages until more is known. PMI’s practice standard describes detailed planning replacing those packages as the project moves forward, and a PMI paper on innovation programs sums up the approach as “plan a little, do a little”.
In the relaunch, the first wave would cover requirements and design at task level, while Build stays a single 8 day block until the design is approved. Once it is, Build breaks into pages, integrations and data migration, each with its own estimate and owner, and the CPM and PERT numbers are recomputed with the finer detail. The rule that keeps rolling wave honest is a fixed cadence for the next wave. Without one, the far end of the schedule stays vague forever and the finish date never firms up.
Monte Carlo simulation
Monte Carlo simulation samples a duration for every task from its range, computes the finish date, and repeats the exercise thousands of times. PMI’s practice standard notes that it can model uncertainty in durations, costs, resources and relationships, and the Scheduling 101 paper points out that the simulator needs three point estimates because it has to know the boundaries of every activity.
We ran 10,000 iterations of the relaunch using the same O, M and P figures as in the PERT section, with a triangular distribution for each task. The results:
The simulation lands later than PERT because a triangular distribution gives the pessimistic tail more weight than the (O + 4M + P) / 6 formula. The two methods make different assumptions about how bad the bad cases get, and it is worth saying which one you used when you quote a date. Simulation also catches merge bias, which PERT misses. When two paths of similar length meet at the same task, the task waits for the slower one. If each path has a 50% chance of being on time independently, the chance that both are is 25%. On the relaunch the second path has 11 days of float, so merge bias barely matters. On a project with three nearly equal paths, it would dominate.
A good practice is to commit to the P80 date externally and manage the team to the P50 date internally.
Where schedules break
Most schedules fail through the way they are maintained, far more often than through a poor choice among project scheduling techniques. These are the patterns that show up again and again:
- Single point estimates. Adding up most likely durations gives a date with a roughly even chance at best, and on the relaunch the real figure was 7% to 18%.
- Assuming people work on the project all day. The Scheduling 101 author plans resources at about 6 hours of work for every 8 hours in organizations that are not purely project based, because meetings and other duties take the rest.
- Hard date constraints instead of logic. A “must finish on” date overrides the dependency calculation, and the critical path stops meaning anything.
- Computing the critical path once. After a crash, a leveling run or a two day slip, a different path can become critical. Recalculate at every status update.
- Compressing tasks that are not critical. Overtime on Content in the example buys nothing, because Content already has 11 days of float.
- Multitasking eating the float. A person splitting time across three projects finishes all three later than if they ran in sequence.
- Never comparing estimates with actual hours. If Build was estimated at 8 days and the last three builds took 11, the next PERT range should say so. Without logged hours per task, nobody notices that the most likely figure has drifted.
After the schedule is set: estimated vs actual hours
The last failure mode is the one most teams can fix fastest, and it is where actiTIME fits. actiTIME is not a scheduling or Gantt tool, and it does not calculate critical paths. It is project time tracking software where the schedule meets reality once work starts: each task carries an estimate and a deadline, people log hours against those tasks, and the gap between the two is visible while there is still time to act.
You set estimated hours and a deadline with reminders on each task, and bulk editing lets you update dozens of them at once when the next wave of work gets detailed. Custom workflow statuses and a kanban board show what is in progress, waiting or done. The Estimated vs. Actual Time Report puts the variance for each task, project or person side by side, which is exactly the history your next three point estimate needs. A time budget on a project or task fills a progress bar as hours come in and turns red once it is exceeded. Because cost of work rates and billing rates sit on the same hours, you can also see what a crash decision really cost and what you can invoice for it.
This is the feedback every technique above depends on. If the schedule says Build takes 8 days and actiTIME shows it took 11 on the last two projects, the next PERT range for Build gets wider and the P80 date moves with it.
Now we can better predict future project requirements
Our company needed a simple way of tracking time used on multiple projects – and actiTIME fit the need. Its interface is simple and easy to maintain. We use the application for time management, task estimation and also to communicate deadline information to our team members. Now having actiTIME we can better predict future project requirements!
actiTIME costs from $5 per user per month, and teams of up to 3 users can keep using it for free. Start a free trial with full features for 30 days, put estimates and deadlines on your next project’s tasks, and compare them with actual hours at the first status meeting.
FAQ
What are L1, L2, L3 and L4 schedules?
They are levels of detail in a schedule hierarchy, used mostly in large engineering, construction and defense programs. As Galorath’s scheduling guide describes them, L1 is the master schedule for executives, L2 tracks key milestones, and L3 and L4 go down to the detailed task level that project managers and team leads work from. The project scheduling techniques in this article run at L3 and L4, and their results roll up into the higher levels.
How is project scheduling done in software projects?
Software teams usually combine rolling wave planning with short iterations. PMI’s Practice Standard for Scheduling notes that agile teams use CPM within each sprint, typically two to four weeks long, and keep the longer horizon at release level. PERT ranges and Monte Carlo are most useful for release dates, where uncertainty is highest and a single figure is least trustworthy.
Is Kanban a project scheduling technique?
Not in the sense used here. Kanban limits work in progress and makes flow visible, which improves throughput, but it does not compute dates, dependencies or a critical path. Teams that run on Kanban still need one of the techniques above, usually a Monte Carlo forecast based on past throughput, when a stakeholder asks when a body of work will be finished.