What Is a Gantt Chart? A Worked Example and the Half Most Teams Leave Out

What's eating up your time? Find out
November 2026
What Is a Gantt Chart? A Worked Example and the Half Most Teams Leave Out

A Gantt chart is a bar chart of a project schedule: tasks run down the left side, time runs across the top, and each task is a bar that starts and ends on its scheduled dates. Arrows between bars show which work has to wait for other work, and a diamond marks a milestone such as a sign off or a launch.

Most guides stop there. The chart Henry Gantt’s colleague Wallace Clark described in 1922 did something more: it showed work planned and work done in the same row, so a manager could see the gap every day. This guide covers the elements of a Gantt chart, a worked example with a critical path, how to make one, how to read progress against it, and where Gantt charts usually go wrong.

What is a Gantt chart?

A Gantt chart is a horizontal bar chart that shows a project schedule over time. Each row is a task, each bar spans the task’s start and finish dates, and the length of the bar is the task’s duration. A modern Gantt chart in project management also shows dependencies between tasks, milestones, who owns each task and how much of it is complete. Project managers use one to schedule work, see what each delay will push back, and show clients and teams the agreed dates on a single page.

You read a Gantt chart from left to right. Find a task in the list, follow its row to the bar, and read the dates above it. Bars that overlap can run at the same time. Bars joined by an arrow cannot: the second one waits for the first. A vertical “today” line, where the tool draws one, shows at a glance which bars should already be finished.

Gantt chart for a website redesign in TeamGantt with tasks grouped into wireframes, design and development phases and bars on a timeline

Compared with a plain task list, the chart adds order and overlap, and it shows which delays will move the end date. What it leaves out is effort: how many hours a task needs and how many have already gone into it. That gap comes back later in this guide.

Elements of a Gantt chart

Guides list anywhere from five to nine elements. These are the ones you will meet in almost every Gantt chart tool, with the mistake that usually comes with each:

Element What it shows Common mistake
Task list The work, usually grouped into phases, on the vertical axis Vague names like “Homepage” instead of “Approve homepage copy”
Timeline Days, weeks or months across the top Forgetting weekends and holidays, so bars look shorter than the real calendar
Task bars Start date, finish date and duration of each task Reading bar length as effort: a 2 day client review may need 1 hour of work
Dependencies Arrows showing which task must start or finish before another Linking tasks only because they sit next to each other in the list
Milestones Zero duration events such as approvals, handoffs and launches, usually diamonds Using a milestone for work that takes time, which hides that work from the schedule
Owners The person or team responsible for each task Giving one person overlapping bars they cannot work on at the same time
Progress Shading inside a bar for the share of the task reported complete Treating a percentage someone typed in as proof the rest will fit before the deadline
Critical path The chain of dependent tasks that sets the earliest finish date, often in red Calculating it once at the start and never again
Baseline A saved copy of the agreed schedule to compare the current one against Overwriting the baseline every time dates move, so slippage disappears

The first five are enough for a small project. Critical path and baseline start to pay off once the project has more than a handful of dependent tasks or a client who asks why the date moved. The milestone element has its own guide: what project milestones are and how to set them.

Where the Gantt chart came from

Henry L. Gantt (1861 to 1919) was an American mechanical engineer who worked on factory production in the years after 1900. The chart carries his name, but the idea of drawing activities as bars on a time scale is older. Karol Adamiecki, a Polish engineer, built a similar chart he called a harmonogram in 1896, and bar charts were already routine on German construction projects by 1912, according to the scheduling historian Patrick Weaver (PM World Journal, 2012).

What made Gantt’s charts different was their purpose. In his book Work, Wages, and Profits he complained that many shops schedule their work beautifully on paper but “have no means of finding out whether those schedules are lived up to or not” (1913 edition, Internet Archive). His charts were filled in at the end of each day with what had actually been produced.

The name “Gantt chart” comes from Wallace Clark’s 1922 book The Gantt Chart: A Working Tool of Management. Clark states the principle on the first pages: work planned and work done are shown in the same space, in relation to each other and to time (Clark, 1922, Internet Archive). He also describes how General William Crozier, Chief of Ordnance, brought Gantt into the US Army Ordnance Department in 1917, where the charts tracked arsenal production during the First World War.

Over the following decades the name stuck to any bar chart of a schedule, and the second half of the original, the record of work done, mostly dropped away. Software brought back progress shading and baselines, but on many teams the chart is still drawn once and then left alone. In our view, putting the “done” side back is the most useful thing you can do with a Gantt chart, and the example below shows why.

Gantt chart example: a website relaunch

An agency is relaunching a client’s website. The team breaks the job into six tasks and estimates each one twice: how many working days it will span on the calendar (duration) and how many hours of work it needs (effort). The figures are illustrative.

Task Depends on Duration and effort
A. Discovery workshop and sitemap Nothing 3 days, 20 hours
B. Copywriting A 5 days, 30 hours
C. Page design A 6 days, 36 hours (designer at 6 hours a day)
D. Client approval B and C 2 days, 3 hours (mostly waiting for the client)
E. Development D 8 days, 96 hours (two developers)
F. Testing and fixes E 3 days, 24 hours

Every link here is finish to start: a task begins the day after its predecessors end. Placing each task as early as its dependencies allow gives the bars on the chart:

A runs days 1 to 3
B runs days 4 to 8, C runs days 4 to 9 (in parallel, both after A)
D waits for the later of B and C: days 10 to 11
E runs days 12 to 19, F runs days 20 to 22
Critical path A, C, D, E, F: 3 + 6 + 2 + 8 + 3 = 22 working days
Float on B: latest finish day 9 minus planned finish day 8 = 1 day
Total estimated effort: 20 + 30 + 36 + 3 + 96 + 24 = 209 hours

The launch milestone sits at the end of day 22. Two things are already visible that a task list would hide. Copywriting has one day of slack, so a small delay there costs nothing, while any delay in design moves the launch day for day. And the client approval bar is two days long but needs only 3 hours of anyone’s time, which is why duration and effort have to be estimated separately. For more on spotting slack, see slack time in project management, and for the full method there is a critical path method template.

How to make a Gantt chart

The steps are the same whether you draw the chart in a spreadsheet or in scheduling software. Most of the work happens before the first bar appears.

  1. Write down the scope and the deadline.

    State what will be delivered, what “done” means and any fixed dates, such as a launch event or a contract end. The chart can only be as clear as this.

  2. Break the work into tasks.

    Split each deliverable until every task can be estimated and owned by one person. A work breakdown structure is the usual way to do this. A common rule of thumb keeps work packages under about 40 hours of effort.

  3. Estimate duration and effort separately.

    Ask the people who will do the work, check how long similar tasks took last time, and include review windows and waiting time. Our guide to project time estimation covers the techniques.

  4. Link dependencies.

    Connect only tasks whose timing really depends on each other. Every extra link makes the schedule harder to change.

  5. Place the bars and find the critical path.

    Schedule each task as early as its predecessors allow, then trace the longest chain of linked tasks. That chain is your end date.

  6. Add milestones and owners, then check workload.

    Mark approvals and handoffs as milestones, assign each task, and look for anyone with overlapping bars they cannot work on at once.

  7. Agree on the chart and save a baseline.

    Walk the team and the client through it, adjust, and save that version. Then decide who updates progress and how often; weekly is a common starting point.

In Excel or Google Sheets: list tasks with a start date and a duration, insert a stacked bar chart, make the start date series invisible so only the duration bars show, and reverse the task axis so the first task sits at the top. Microsoft also publishes ready made Gantt chart templates for Excel. A spreadsheet is fine for a short task list. Once dependent dates start moving, shifting them by hand turns into the main job.

If you would rather start from a filled in structure, our project schedule template and the guide to designing a project timeline cover the same ground with a downloadable file.

Reading progress: the planned and the done

Go back to the website relaunch. It is the end of day 9, the day page design is due to finish. Copywriting finished on time. The designer has logged 33 hours on page design against the 36 hour estimate and reports the pages as 60% done.

On a chart that only shows progress shading, the design bar is 60% filled and ends today. It looks a bit behind. The hours tell a different story:

Hours used: 33 of 36 estimated = 92% of the budget
Projected total effort: 33 / 0.60 = 55 hours
Hours still needed: 55 minus 33 = 22 hours
At 6 hours a day: 22 / 6 = 3.7, so about 4 more working days
Design finishes on day 13 instead of day 9, and because design is on the critical path, launch moves from day 22 to day 26
Effort overrun on design: 55 minus 36 = 19 hours, or 53%

The same slip on copywriting would have cost less: with 1 day of float, a 4 day delay there moves the launch by 3 days, and a 1 day delay moves it by nothing. So the critical path also tells you which variances to chase first.

Clark made the same point a century ago. A bar shows the plan, and the problem only becomes visible when what was actually done sits beside it, and the cheapest measure of “done” most teams already have is hours tracked against each task’s estimate. When hours used run ahead of reported progress, the bar is going to stretch. For more ways to check status, see project progress monitoring.

Gantt chart vs timeline, Kanban board and PERT chart

These formats answer different questions, and many teams use two of them on the same project.

Format What it answers Choose it when
Gantt chart When each task happens, in what order and what it delays Tasks depend on each other and a date matters
Project timeline What the key phases and milestones are, at a glance You are presenting to a client or executives who do not need every task
Kanban board What state each task is in right now and where work piles up Work arrives continuously and order matters more than dates
PERT chart How tasks connect as a network and how uncertain the durations are You need three point estimates before committing to a schedule

A timeline is a simplified Gantt chart with the task detail removed; the project timeline guide shows how to build one. Kanban is covered in what is Kanban. Gantt charts are most at home in sequential projects run with the waterfall methodology, though agile teams often keep one at release level while daily work moves on a board.

Where Gantt charts go wrong

When a Gantt chart stops being useful, the cause is usually how it is kept rather than the format. These are the patterns project managers describe most often:

  • Drawn once, never updated. The chart from the kickoff meeting becomes a picture of an old plan. People stop checking it, and the real schedule moves into chat threads.
  • Progress by feel. Percent complete is whatever the owner types in. Without hours or finished deliverables behind it, 60% can mean anything, as the design task above shows.
  • Duration mistaken for effort. A 10 day bar for a part time specialist is read as 80 hours of capacity that does not exist, or a 2 day client review is staffed as if it were 16 hours of work.
  • Too much detail. Hundreds of rows make the critical path impossible to see. Keep the chart at the level people make decisions on and push task detail into a list or board.
  • Dependencies on everything. Linking every task to the one above it creates a fragile schedule in which any change ripples through dates that did not need to move.
  • Separate charts, shared people. In companies running several projects, each manager’s chart looks fine on its own while the same designer is booked on three of them in the same week.
  • False precision. Exact dates on exploratory work imply a certainty nobody has. Schedule a research window and a decision milestone instead, then add detail once the work is clearer.

Most of these come down to the same thing: the chart records intentions, and nobody feeds it facts. A weekly look at hours tracked against each task’s estimate fixes the first three on the list.

Tools for making a Gantt chart

You do not need dedicated software for a small project, but past a few dozen linked tasks it saves hours of moving dates by hand. Prices below come from each vendor’s own pricing page.

Tool Best fit Verified details
Excel or Google Sheets Short task lists with one person editing Stacked bar chart or a template; dependencies do not move dates automatically
TeamGantt Small teams that want a shared, easy to read chart Base option $59 per month flat for 1 manager, 10 collaborators, 5 projects and 150 tasks per project; 14 day trial
GanttPRO Teams that need critical path and baselines on every plan From $7 per user per month billed annually; critical path, baseline and dependencies included from the first tier
ProjectLibre Teams moving off Microsoft Project files Opens .mpp files; free desktop download, cloud from $9.99 per user per month billed annually

Sources: TeamGantt pricing, GanttPRO pricing, ProjectLibre. For a wider comparison, see our roundup of project planning software.

Tracking actual hours against the chart in actiTIME

actiTIME does not draw Gantt charts. It covers the other half of Clark’s principle, the record of work done: how many hours went into each task compared with its estimate. Teams keep their Gantt chart in whichever scheduling tool they like and use actiTIME to see whether the bars are telling the truth.

Here is how the website relaunch would look in actiTIME:

  • The client becomes a customer, the relaunch is a project, and the six bars are tasks. Each task gets an estimate (36 hours for page design), a deadline matching the end of its bar, and a workflow status. Tasks can be created in bulk or imported from CSV.
  • People log hours on those tasks in a weekly timesheet, in Calendar View with start and stop times, or from the mobile app.
  • In the Kanban view every task card shows hours against the estimate, for example 26:15 of 40:00, so a task burning through its hours shows up before its deadline arrives.
  • The Estimated vs. Actual Time Report lists spent time, estimated time and the difference in hours and percent for each customer, project and task, broken down by user.
  • A time budget on the project tracks hours invested against hours allocated, and a progress bar turns red when the budget is exceeded.
actiTIME Tasks in Kanban view grouped by project, with tracked hours shown against the estimate on each task card

In the relaunch example, the design task would show 33:00 of 36:00 on day 9 while its status still says In Progress. That is the signal to ask the designer how much is left, recalculate, and move the bars on the Gantt chart before the client hears about the launch date from someone else.

actiTIME Estimated vs. Actual Time Report showing spent time, estimated time and variance in hours and percent for each task and user

Because those hours are recorded anyway, they also feed the Billing Summary Report, PDF invoices and the Cost of Work Report, so the same entries that check the schedule also bill the client. Task estimates and budgets are part of the paid version; actiTIME is free for up to 3 users, and paid options start from $5 per user per month.

Now we can better predict future project requirements

Our company needed a simple way of tracking time used on multiple projects – and actiTIME fit the need. Its interface is simple and easy to maintain. We use the application for time management, task estimation and also to communicate deadline information to our team members. Now having actiTIME we can better predict future project requirements!

Start a free trial of actiTIME with full features for 30 days. After the trial, teams of up to 3 users can keep using it for free.

FAQ

What has replaced the Gantt chart?

Nothing has replaced it for projects where tasks depend on each other and dates matter. Kanban boards and backlogs took over day to day work in many software teams, but those teams often still keep a Gantt chart or a timeline at release level. What changed is the medium: charts that were once redrawn on paper now recalculate automatically when a date moves.

Can AI make a Gantt chart?

Yes, as a first draft. Several Gantt chart tools, including TeamGantt and GanttPRO, offer AI makers that suggest phases, tasks and durations from a short description, and general chatbots can produce a task table you paste into a spreadsheet. The draft does not know your team’s availability or your client’s review habits, so check every duration and dependency with the people doing the work.

Is a Gantt chart useful for a one person project?

Often less than people expect. When you are the only resource, every task runs in sequence and a dated task list does most of the job. A Gantt chart still helps when the project depends on other people, such as approvals, suppliers or government filings with lead times, because it shows where waiting time will hold you up.